    Acceptance of the Prut bridge at Ungheni postponed until March 2028

    Romania's Ministry of Transport has postponed until March 2028 the acceptance of the Prut bridge at Ungheni, by almost a year and a half compared to the initial deadline. The ministry makes acceptance conditional on the completion of works both on the bridge and at the border crossing point. The precise moment when traffic will be able to use the new bridge has not been announced. 1 2 3 4

    5 outlets Importance 86

    Satelit AI summary from 4 outlets Every statement shows its source.

    What is known

    • The new deadline appears in a reply from the Ministry of Transport to an interpellation by Romanian MP Alexandru Muraru. 1 3
    • Works on the bridge began in April 2025, but the building permit for one of the two sections was issued only on 17 June 2026. 1 2
    • The order to start works was given on 15 September, and from that date the Romanian authorities calculate an 18-month period for execution. 2 3
    • The contractor Ness Proiect Europe was initially supposed to finish the bridge by 26 October 2026, and at the beginning of the year some officials pointed to July. 1 4
    • In October, CNAIR reported physical progress of 56% and indicated December 2027 as the deadline for completing the works. Now the ministry estimates acceptance three months later still. 1 2
    • At the border crossing point there will be control booths, as well as platforms and halls where goods will be inspected, and cars, buses and trucks will each have separate lanes. 1 3
    • Until the A8 motorway is completed, drivers coming from Iași will reach the bridge by a temporary route of about 18 kilometres. CNAIR is still preparing the study for the modernisation of the DN 28G national road. 1 4
    • On the Republic of Moldova side, the temporary solution is a road of about 500 metres linking the bridge to the ring road of Ungheni municipality. 2 3
    • The 2.77-kilometre section of the A8 motorway between Golăiești and the bridge is to be built as a priority, but the contract with the Italian group Itinera is blocked by legal problems. 1 4

    Key figures

    March 2028
    the new deadline for acceptance of the investment 1
    56%
    physical progress reported by CNAIR in October 2
    18 months
    execution period calculated from the order to start works 1
    about 18 kilometres
    temporary route from Iași to the bridge 1
    2.77 kilometres
    length of the A8 section between Golăiești and the bridge 3

    What is not known yet

    • The day when drivers will start crossing the Prut on the new bridge has not been announced. 2 4
    • The capacity of the DN 28G national road to bear heavy-tonnage traffic has not been established. 1

    Timeline

    1. Works on the bridge begin. 1

    2. The building permit is issued for one of the two sections of the project. 2

    3. The order to start works is given, from which the 18-month period is calculated. 3

    4. The contractor's initial deadline for completing the bridge. 1

    5. In October, CNAIR indicates December 2027 as the deadline for completing the works. 2

    6. The Ministry of Transport estimates acceptance of the entire investment in March 2028. 4

    Sources

    1. Bani.md
    2. Stiri.md
    3. Știri pe surse
    4. Realitatea.md
    How it is written

    Satelit AI writes only what the numbered sources below report. Every statement links to them, and figures and names are compared with their text before publication.

    Comments on Satelit

    Sign in to comment

    No links or contact details. We read your first comments before they appear.

    No comments yet. Be the first.

    Comments on other sites

    • это очередной кластер!)

      2 likes · Point.md · 26 Nov, 18:43

    No names. Phones and addresses are hidden.

    On the same topic

    65

    Roads & utilities

    Authorities plan to expand road charges, including e-Vignette, to raise money for modernisation

    Bani.md: Autoritățile Republicii Moldova intenționează să extindă sistemele de taxare pentru utilizarea infrastructurii rutiere, inclusiv sistemul electronic „e-Vinieta”, pentru a identifica resurse suplimentare necesare modernizării transporturilor, potrivit Programului de dezvoltare a transporturilor și…

    Trust 70 · 3 outlets

    Report this comment

    Report this comment

    Cookies on Satelit

    The necessary cookies (language, theme, city, account) are always on. With your consent we also use Google Analytics, Microsoft Clarity and Yandex Metrica to see which pages are used and where visitors stop. No advertising cookies.

    Details